A costed recipe for every product
Each finished item needs its components, quantities, units and normal wastage written down, plus the operations that turn them into the product. Without that recipe there is no reliable cost per unit to quote from.
ERP for manufacturing
Manufacturing accounting means the books follow the material: what you bought, what went into production, what came out, what it cost and what you sold, with GST on both sides. Fininvo ERP keeps sales orders, bills of materials, MRP, work orders, goods receipts, invoices and the ledger in one system, so a figure in the accounts can be traced back to the order, receipt or work order behind it.
What the industry needs
A trader buys and sells the same item. A manufacturer turns many items into one, so stock, cost and tax all change shape on the way through the factory.
Each finished item needs its components, quantities, units and normal wastage written down, plus the operations that turn them into the product. Without that recipe there is no reliable cost per unit to quote from.
Production should start from what customers have confirmed, net of what is already in stock or on order. Planning from last month's shortages leaves some lines idle and others short.
Supervisors need to see which jobs are running, paused or done, and record good output and scrap with a reason, so rejection is measured instead of argued about.
Bad raw material is cheapest to catch before it enters stock. Receipts need a pass or fail per line, with the reason recorded for the supplier conversation.
Raw material should be valued at what was actually paid, per warehouse, so the stock figure on the balance sheet and the cost of goods sold come from the same records the stores team uses.
Every product needs an HSN code and rate, every unit a GST unit code for the HSN summary, and purchase tax has to be matched against what suppliers reported before credit is claimed.
Fininvo modules
All of these sit in one Fininvo ERP workspace and share the same products, warehouses and customers.
| Need | Fininvo module | How it covers it |
|---|---|---|
| Product recipe | Bill of materials | Component lines with quantity, unit, scrap % and a critical flag; operations with work center, setup and run minutes and hourly rates; a live cost per unit; versions; explode for any batch quantity. |
| Planning | MRP | Runs over a 7 to 365 day horizon on confirmed and in-progress sales orders. Net requirement is gross minus available stock minus quantity on order. Made items become work order suggestions, bought items purchase suggestions. |
| Production | Work orders and shop floor | A work order takes its material lines from the BOM. It moves through plan, release and start; the shop floor board starts, pauses and resumes jobs and records good and scrap quantities with a reason code. |
| Inward quality | Quality | Mark a goods receipt as QC required and pass or fail each line with a rejection reason. Inspection plans, inspection lots with a usage decision, and a defect log sit in the same module. |
| Buying | Purchase orders and GRN | Create the GRN from the purchase order. Accepted quantities update what is received on each PO line and move the PO to Partially Received or Received. |
| Stock and valuation | Inventory | Stock per warehouse. An accepted GRN values the receipt at the PO price and updates the moving average cost. Products can track batch, expiry and serial numbers. Stock adjustments go through submit and approve. |
| Selling | Sales orders and invoicing | Confirming a sales order checks the customer credit limit and reserves stock. Create Delivery and Create Invoice start from the order; shipping the delivery takes the goods out of stock at cost. |
| Books | Accounting | General ledger, receivables, payables, bank reconciliation and month-end close in the same system as the stock and sales records. |
| GST returns | Tax export | GSTR-1 for a month and GSTIN as JSON, Excel or CSV, with B2B, B2CS and HSN summary sections, plus a GSTR-3B summary file. You review and upload on the GST portal. |
Worked example
A workshop makes four-shelf steel storage racks. A customer orders 50 for delivery in three weeks. This is how that order moves through Fininvo ERP, including the steps you still do by hand today.
The order for 50 racks is entered with the delivery date. Confirming it checks the customer's credit limit against open balances and reserves the 8 racks already in the finished goods warehouse. A draft quotation would not count; only confirmed or in-progress orders feed planning.
The rack is set up as a manufactured product, so MRP compares 50 ordered with 8 available and nothing on order, and suggests a work order for 42. Anything on the order that you buy rather than make would appear as a purchase suggestion dated for the delivery date.
Approving creates a planned work order for 42 racks against the active bill of materials. Its material lines are the BOM quantity per rack multiplied by 42: steel sheet, angle uprights, bolt kits and powder coat. The table below shows those numbers.
The buyer compares the material lines with stock and raises purchase orders for the shortfall in sheet and bolt kits. A PO counts as open supply in the next MRP run once it is confirmed, so the same shortage is not ordered twice.
The sheet and bolt kits arrive on one delivery, together with a carton of spare shelf clips from the same purchase order. The GRN is created from the PO and marked QC required. The inspector passes the sheet and bolt kit lines and fails the clips line, recording the reason, and the clips are entered as rejected rather than accepted. Accepting the GRN puts the accepted quantities into stock, valued at the PO price, and the purchase order shows Partially Received until replacement clips arrive.
The planner plans and releases the work order and production starts from the shop floor board. At the end of the shift the supervisor records 40 good racks and 2 scrapped with a weld-defect reason code. The work order now shows 40 completed and 2 rejected against 42 planned.
Today the work order screens do not move stock by themselves. The stores team records the material issued and the 40 finished racks received as a stock adjustment, which is submitted and approved, so the raw material falls and the finished goods rise in the right warehouse.
From the sales order, Create Delivery for 48 racks: the 8 in stock plus the 40 just made. Shipping the delivery takes them out of stock at cost and the order shows Partially Delivered. Create Invoice raises the GST invoice with the HSN code and rate from the product. The last 2 racks go on the next run.
At month end, open Tax export, pick the month and the GSTIN, and download GSTR-1 as JSON, Excel or CSV. Review the B2B lines and HSN summary, then upload the file on the GST portal. The GSTR-3B summary downloads the same way. Fininvo prepares the files; you file on the portal.
The example in numbers
Material lines are the BOM quantity per rack x 42. The buyer orders the shortfall.
| Material | Unit | Per rack (BOM) | Work order line (x 42) | In stock | To buy |
|---|---|---|---|---|---|
| Steel sheet | kg | 9.5 | 399 | 250 | 149 |
| Angle upright | piece | 4 | 168 | 200 | 0 |
| Bolt kit | set | 1 | 42 | 10 | 32 |
| Powder coat | kg | 0.3 | 12.6 | 5 | 7.6 |
Two things to notice. The work order line for sheet is 399 kg, which is 9.5 x 42 with no wastage added. If your BOM carries a scrap percentage for cutting losses, add that allowance when you order sheet, because work order lines do not add it today. And the uprights need no purchase at all: 200 in stock covers 168.
On the output side, 42 planned became 40 good and 2 rejected, a 4.8% rejection on this run. Those two figures sit on the work order, next to the planned quantity, so the next costing review starts from recorded numbers rather than memory.
Manufacturing accounting
Raw material comes in at what you paid. When a GRN is accepted, each accepted line is valued at its purchase order price and the product's moving average cost for that warehouse is recalculated under a lock, so two receipts at the same moment cannot corrupt the average. Free-text lines that are not products create no stock.
Goods go out at cost. Shipping a delivery note issues the stock at its valued cost and your company's negative stock policy decides whether a shortage blocks the shipment or only warns. That is the cost that sits behind the sale.
Production costs are reviewed on the work order. The Costing area has cost standards per item, activity rates for each work center, a cost view on every work order, variance reports and WIP valuation. From the work order cost view you can post the costs to the ledger as a journal that debits work in progress. Your chart of accounts needs WIP inventory, inventory, wages and overhead accounts for that posting, and an open fiscal period. Review the cost lines before posting; they are only as good as the activity rates you set.
Then the close. Receivables, payables and bank reconciliation run in the same ERP, and the month-end close checklist locks the period once the stock and production entries for the month are in. If you are comparing products, the accounting features page lists the ledger and reporting side in full.
GST and people
Give every product its HSN code and GST rate and every unit its GST unit code; the HSN summary in GSTR-1 reads them. If you have more than one GST registration, the export asks which GSTIN to build the file for, so each registration gets its own return. The multi-GSTIN page covers branches and stock transfers between them.
On purchases, match the tax on supplier bills with what suppliers filed before you rely on the credit. The GSTR-2B reconciliation and input tax credit pages show how that works in Fininvo today.
Goods leaving the factory above the e-way bill limit need a bill before they move. In Fininvo you prepare the e-way bill details as a draft and print them; the e-way bill number itself is generated on the government e-way bill portal. The same applies to e-invoice IRNs on the invoice registration portal. See the e-way bill page for the exact steps.
Shift workers, attendance and wages usually sit next to production planning. Fininvo HRMS and Payroll are separate products that share the same login: shift management for rosters and PF and ESI compliance for the statutory side of factory payroll.
Straight answers
Better to read it here than find it in the second week of a trial.
Recording output and completing a work order update the work order, not the stock ledger. Record the material issue and the finished goods receipt as an approved stock adjustment, as in step 7.
The run does not explode a finished product down to component level and does not apply safety stock or lot sizing. Component needs appear on the work order's material lines.
The BOM records scrap %, but work order material lines are BOM quantity times the planned quantity. Add the wastage allowance when you buy.
Subcontract orders (Enterprise plan) record components sent to a job worker, what the job worker holds, and quantities received and rejected. They do not move stock in your warehouses, print a job work challan or prepare ITC-04.
A work order produces one finished product. Co-products and by-products from the same run have to be recorded separately.
Fininvo prepares GSTR-1 and GSTR-3B files for upload. It does not file returns with GSTN, and IRN and e-way bill numbers are generated on the government portals.
It is accounting that follows material through the factory: purchases valued into stock, material used in production, finished goods, cost of goods sold and GST on both purchases and sales. Fininvo ERP does this alongside BOMs, MRP and work orders, so the ledger and the production records come from the same system.
Yes. The Manufacturing module has bills of materials with scrap %, operations and a cost per unit, and an MRP run that turns confirmed sales orders into work order and purchase suggestions. Approving a work order suggestion creates a planned work order whose material lines come from the active BOM.
At the purchase order price when the goods receipt is accepted, with the moving average cost per product and warehouse recalculated on every receipt. Deliveries issue stock at that valued cost.
Not today. Recording output and completing a work order update the work order quantities and status. Post the material issue and the finished goods receipt with a stock adjustment, which is submitted and approved like any other adjustment.
Fininvo prepares them. You download GSTR-1 as JSON, Excel or CSV for a month and GSTIN, and a GSTR-3B summary, then review and upload them on the GST portal. Direct filing from Fininvo is not available.
On the Enterprise plan, subcontract orders track the components you send to a job worker, the stock the job worker holds, and what comes back as received or rejected. Job work challans and ITC-04 are not prepared by Fininvo today.